CLUB HOUSE : Deck slab casting, above roof structural work & blockwork completed; Internal finishing work & Tiling work in progress as on 1/10/2020
Block-12 : Roof floor slab casting & 8th floor brick work completed; 9th floor brick work & internal plaster work in progress as on 1/10/2020
Block-13 : Structural work & external plaster work completed; Internal finishing work in progress as on 1/10/2020
Block-11 : Structural work, internal & external plaster work completed, internal finishing work & tiling work in progress as on 1/10/2020
Block-10 : Structural work, internal & external plaster work completed; Internal finishing work & tiles work in progress as on 1/10/2020
Block-9 : Internal plaster & external plaster work completed; Tiles work, Outside paint work & other finishing work in progress as on 1/10/2020
Block-8 : External plaster, Internal plaster & structural work completed; internal finishing work & outside paint work in progress as on 1/10/2020
Block-7 : Final Finishing Work in progress as on 1/10/2020
Block-6 : Final Finishing Work in progress as on 1/10/2020
Block-4 : Final finishing work going in progress as on 1/10/2020
Block 2 : 10th floor brick work completed; Above roof structural work & 11th floor brick work in progress as on 1/10/2020
Block-1 : Outside elevation brick work, plaster work & Inside plumbing work in progress as on 1/10/2020
Block-3 : Structural Brick Work; External Plaster work & Internal plaster work completed; Finishing work & Outside paint work in progress as on 1/10/2020