ERROR:
Javascript not activated
×
AS ON 01.02.2024
TOWER-1
Part deck slab completed, balance work in progress.
TOWER-2
Piling work completed.
Excavation and sub structure work in progress.
TOWER-3
Roof floor slab casting done.
TOWER-4
STP, UGR, Fire Pump Room Completed upto 2nd floor.
Up to 2nd floor slab part slab completed.
Balance part shuttering on progress.
TOWER-5
4th floor slab casting completed.
5th floor slab casting work in progress.
TOWER-6
1st floor & 2nd floor brick work completed .
3rd floor brick work in progress.
4th floor slab casting completed.
TOWER-7
9th floor slab casting completed.
10th floor slab ready for casting .