ERROR:
Javascript not activated
×
AS ON 01.11.2024
TOWER-1
2nd floor slab casting done.
TOWER-2
Part ground floor slab completed.
Part 1st floor slab casting done.
Balance part sub structure work in progress.
TOWER-3
Roof slab casting done.
Above roof work in progress.
Finishing work in progress.
Model floor work in progress.
TOWER-4
3rd floor internal brick work completed.
Hence necessary demand for the said work should be raised accordingly.
7th floor partition wall work completed.
3rd floor internal brick work completed.
TOWER-5
11th floor slab casting done.
Roof slab work in progress.
Upto 7th floor brick work done.
8th floor brick work in progrss.
5th floor plaster work completed.
7th floor internal brick work completed.
TOWER-6
5th floor level slab mivan shuttering work in progress.
3rd floor brick work and plaster completed.
TOWER-7
Roof slab completed.
Above roof work in progrss
Internal plumbing work in progrss.
Water proofing work in progress.