AS ON 01.08.2023
Block-1
STRUCTURAL WORK ABOVE ROOF IN PROGRESS.
BLOCK WORK(INTERNAL) COMPLETED.
DOOR FRAME FIXING COMPLETED.
PLASTER (INTERNAL) COMPLETED
POP & PUTTY CEILING COMPLETED.
ELECTRICAL WORK (CHASECUTTING & BOX FIXING) COMPLETED.
ELECTRICAL WORK (DB & JUNCTION BOX FIXING) COMPLETED.
PLUMBING WORK (INTERNAL PIPE FIXING) COMPLETED.
WATER PROOFING (TOILET & KITCHEN) COMPLETED.
FIRE WORK (PIPE FIXING & WELDING) COMPLETED.
ELEVATION WORK (EXTERNAL BLOCKWORK &PLASTER) A & C FLAT & D FLAT COMPLETED. B FLAT IN PROGRESS.
FLOORING WORK A FLAT IN PROGRESS.
Block-2
Flats Handover in Progress .
Block-3
Flats Handover in Progress .
Block-4
Flats Handover in Progress .