AS ON 01.05.2022

    CLUSTER 12(ROW HOUSE NO. 221-228):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 221-228.
  • Finishing works, flooring work and on or before possession in progress.
    CLUSTER 13(ROW HOUSE NO. 216-220):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 216 - 220.
  • Finishing works, flooring work and on or before possession in progress.
    CLUSTER 14(ROW HOUSE NO. 199-210):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting, brick work completed for row house no. of 199 -210.
  • Flooring work of unit no.199 work in progress.
  • Flooring work of unit no. 200 -210 completed. 
  • Finishing work and on or before possession in progress. 
    CLUSTER 15(ROW HOUSE NO. 211-215):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 211-215.
  • Finishing works, flooring work and on or before possession in progress.
    CLUSTER 16(ROW HOUSE NO. 187-198):
  • Ground floor slab casting work completed for unit no 187-196, 1st floor slab casting, roof floor slab casting work completed for unit no. 187-191.
  • Brick work completed for unit no. 187-198. Flooring work completed for unit no. 187-189 and unit no.190 -191 flooring work in progress.
  • Finishing work and on or before possession for unit no. 187-191 in progress.
    CLUSTER 17(ROW HOUSE NO. 178-186):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 178-186.
  • Finishing works, flooring work and on or before possession in progress.
    CLUSTER 19(ROW HOUSE NO. 163-167):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 163 -167.
  • Flooring work completed for unit 163 &164 and 165 -167 flooring work in progress.
  • Finishing works and on or before possession in progress.
    CLUSTER 20(ROW HOUSE NO. 168-177):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 168-175.
  • Flooring work completed for unit no. 169 &175 and unit no.168 flooring work in progress.
  • Finishing works, and on or before possession for unit no. 168 -175 in progress.
    CLUSTER 21(ROW HOUSE NO. 153-157):
  • Ground floor slab casting works completed for unit no. 153-155.
  • Brickwork in progress for unit no. 153-157.
    CLUSTER 22(ROW HOUSE NO. 148-152):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 148-152.
  • Finishing works, flooring work and on or before possession in progress.
    CLUSTER 23(ROW HOUSE NO. 138-147):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no.140-147.
  • Flooring work completed for unit no.140-146 and unit no.147 flooring work in progress.
  • Finishing works and on or before possession in progress.
    CLUSTER 26(ROW HOUSE NO. 118-127):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 118 -127.
  • Flooring work completed for unit no.122-125 and unit no. 118 -121 & 126 flooring work in progress.
  • Finishing works and on or before possession in progress.
    CLUSTER 27(ROW HOUSE NO. 107-115):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 107 -115.
  • Flooring work completed for unit no.108-111 and unit no. 107 & 112 -115 flooring work in progress.
  • Finishing works and on or before possession in progress.
    CLUSTER 28(ROW HOUSE NO. 128-137):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 128-135.
  • Finishing works, flooring work and on or before possession in progress.
    CLUSTER 29(ROW HOUSE NO. 98-106):
  • Ground floor slab casting and 1st floor slab casting work completed for unit no. 98-106, roof floor slab casting work completed for unit no. 99 -106.
  • Brick work completed for unit no. 101-106 and unit no. 98 -100 flooring work in progress.
  • Finishing works, flooring work and on or before possession in progress for unit no. 101-106
    CLUSTER 33(ROW HOUSE NO. 71-81):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 71-81.
  • Flooring work completed for unit no. 80 & 81 and unit no. 71-79 flooring work in progress.
  • Finishing works and on or before possession in progress.
    CLUSTER 34(ROW HOUSE NO. 53-64):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting, flooring work and brick work completed for unit no. 53-64.
  • Finishing works and on or before possession in progress.
    CLUSTER 35(ROW HOUSE NO. 82-90):
  • Ground floor slab casting, 1st floor slab casting and roof floor slab casting completed for unit no. 82-84.
  • Brick works for unit no 82-84 in progress.
    CLUSTER 36(ROW HOUSE NO. 43-52):
  • Ground floor slab casting, 1st floor slab casting and roof floor slab casting completed for unit no. 49-52.
  • Brick works for unit no. 49-52 in progress.
    CLUSTER 39(ROW HOUSE NO. 1-11):
  • Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 1-11.
  • Flooring work completed for unit no. 1-9.
  • Finishing works and on or before possession in progress.
    Club:
  • Foundation work completed.
  • Plinth Slab casting work completed.
  • 1st floor ground floor casting work completed.
  • 2nd floor slab work in progress.
  • Brick work at ground floor work in progress.