ERROR:
Javascript not activated
×
AS ON 01.05.2022
CLUSTER 12(ROW HOUSE NO. 221-228):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 221-228.
Finishing works, flooring work and on or before possession in progress.
CLUSTER 13(ROW HOUSE NO. 216-220):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 216 - 220.
Finishing works, flooring work and on or before possession in progress.
CLUSTER 14(ROW HOUSE NO. 199-210):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting, brick work completed for row house no. of 199 -210.
Flooring work of unit no.199 work in progress.
Flooring work of unit no. 200 -210 completed.
Finishing work and on or before possession in progress.
CLUSTER 15(ROW HOUSE NO. 211-215):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 211-215.
Finishing works, flooring work and on or before possession in progress.
CLUSTER 16(ROW HOUSE NO. 187-198):
Ground floor slab casting work completed for unit no 187-196, 1st floor slab casting, roof floor slab casting work completed for unit no. 187-191.
Brick work completed for unit no. 187-198. Flooring work completed for unit no. 187-189 and unit no.190 -191 flooring work in progress.
Finishing work and on or before possession for unit no. 187-191 in progress.
CLUSTER 17(ROW HOUSE NO. 178-186):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 178-186.
Finishing works, flooring work and on or before possession in progress.
CLUSTER 19(ROW HOUSE NO. 163-167):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 163 -167.
Flooring work completed for unit 163 &164 and 165 -167 flooring work in progress.
Finishing works and on or before possession in progress.
CLUSTER 20(ROW HOUSE NO. 168-177):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 168-175.
Flooring work completed for unit no. 169 &175 and unit no.168 flooring work in progress.
Finishing works, and on or before possession for unit no. 168 -175 in progress.
CLUSTER 21(ROW HOUSE NO. 153-157):
Ground floor slab casting works completed for unit no. 153-155.
Brickwork in progress for unit no. 153-157.
CLUSTER 22(ROW HOUSE NO. 148-152):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 148-152.
Finishing works, flooring work and on or before possession in progress.
CLUSTER 23(ROW HOUSE NO. 138-147):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no.140-147.
Flooring work completed for unit no.140-146 and unit no.147 flooring work in progress.
Finishing works and on or before possession in progress.
CLUSTER 26(ROW HOUSE NO. 118-127):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 118 -127.
Flooring work completed for unit no.122-125 and unit no. 118 -121 & 126 flooring work in progress.
Finishing works and on or before possession in progress.
CLUSTER 27(ROW HOUSE NO. 107-115):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 107 -115.
Flooring work completed for unit no.108-111 and unit no. 107 & 112 -115 flooring work in progress.
Finishing works and on or before possession in progress.
CLUSTER 28(ROW HOUSE NO. 128-137):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 128-135.
Finishing works, flooring work and on or before possession in progress.
CLUSTER 29(ROW HOUSE NO. 98-106):
Ground floor slab casting and 1st floor slab casting work completed for unit no. 98-106, roof floor slab casting work completed for unit no. 99 -106.
Brick work completed for unit no. 101-106 and unit no. 98 -100 flooring work in progress.
Finishing works, flooring work and on or before possession in progress for unit no. 101-106
CLUSTER 33(ROW HOUSE NO. 71-81):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 71-81.
Flooring work completed for unit no. 80 & 81 and unit no. 71-79 flooring work in progress.
Finishing works and on or before possession in progress.
CLUSTER 34(ROW HOUSE NO. 53-64):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting, flooring work and brick work completed for unit no. 53-64.
Finishing works and on or before possession in progress.
CLUSTER 35(ROW HOUSE NO. 82-90):
Ground floor slab casting, 1st floor slab casting and roof floor slab casting completed for unit no. 82-84.
Brick works for unit no 82-84 in progress.
CLUSTER 36(ROW HOUSE NO. 43-52):
Ground floor slab casting, 1st floor slab casting and roof floor slab casting completed for unit no. 49-52.
Brick works for unit no. 49-52 in progress.
CLUSTER 39(ROW HOUSE NO. 1-11):
Ground floor slab casting, 1st floor slab casting, roof floor slab casting and brick work completed for unit no. 1-11.
Flooring work completed for unit no. 1-9.
Finishing works and on or before possession in progress.
Club:
Foundation work completed.
Plinth Slab casting work completed.
1st floor ground floor casting work completed.
2nd floor slab work in progress.
Brick work at ground floor work in progress.