AS ON 01.08.2023
CLUSTER 01(ROW HOUSE NO. 298-303 ):
Civil sub structure work completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 02(ROW HOUSE NO. 290,291 ):
Civil sub structure work completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 03(ROW HOUSE NO. 292-297):
Civil sub structure work under completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 04(ROW HOUSE NO. 288,289):
Civil sub structure work completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 05(ROW HOUSE NO. 285-287 ):
Civil sub structure work under completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 06(ROW HOUSE NO. 271-284):
Civil sub structure work under completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 07(ROW HOUSE NO. ):
Civil sub structure work under completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 08(ROW HOUSE NO. 254-259):
Civil sub structure work completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 09(ROW HOUSE NO. 260-270):
Civil sub structure work under completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 10(ROW HOUSE NO. 248-253):
Civil sub structure work completed.
Civil super structure work under progress.
Internal brick work under progress.
Inside & outside area plaster under progress.
CLUSTER 11(ROW HOUSE NO. 229-236 ):
Civil sub structure work completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 12(ROW HOUSE NO. 221-228):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed.
Window work under progress.
Internal putty work under progress.
Tiling work completed.
Plumbing work completed.
Internal electrification work completed.
External plastering work completed.
CLUSTER 13(ROW HOUSE NO. 216-220):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed.
Window work completed.
Tiling work completed.
Internal electrification work completed.
Plumbing work completed.
External plastering work completed
CLUSTER 14(ROW HOUSE NO. 199-210):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed.
Door shutter work under progress.
Window work completed.
Internal putty work under progress.
Tiling work completed.
Plumbing work completed.
Internal electrification work completed.
External plastering work completed & external painting work under progress.
CLUSTER 15(ROW HOUSE NO. 211-215):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed.
Window work under progress.
Plumbing works completed.
Internal putty work completed.
Tiling works under progress.
Internal electrification work completed.
External plastering works completed & external painting works under progress.
CLUSTER 16(ROW HOUSE NO. 187-198):
Civil sub structure work completed.
Civil super structure completed for Phase I unit & under progress for other Phases.
Internal brick works & plastering completed for Phase I units & under progress for other Phases.
Door frame fixing work completed for Phase I unit.
Window work completed for phase I unit.
Internal putty work under progress.
Tiling works completed for Phase I unit & under progress for other Phases.
Plumbing work completed.
Internal electrification work completed.
External plastering work completed for Phase I unit & external painting for phase I unit under progress.
CLUSTER 17(ROW HOUSE NO. 178-186):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed.
Window work under progress.
Internal Plumbing work completed.
Internal putty work under progress.
Internal electrification work under progress.
External plastering work completed.
CLUSTER 18(ROW HOUSE NO. 158-162):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed.
Window work under progress.
Internal putty work under progress.
Tiling works under progress.
Plumbing work under progress.
Internal electrification work completed.
External plastering work completed.
CLUSTER 19(ROW HOUSE NO. 163-167):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed.
Door shutter work under progress.
Window work completed.
Internal putty work completed.
Tiling work completed.
Plumbing work completed.
Internal electrification work completed.
External plastering work & external painting work under progress.
CLUSTER 20(ROW HOUSE NO. 168-177):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed.
Door shutter work under progress.
Window work completed.
Internal putty work completed.
Tiling work completed.
Plumbing work completed.
Internal electrification work completed.
External plastering works completed & external painting works under progress.
CLUSTER 21(ROW HOUSE NO. 153-157):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed.
Window work under progress.
Internal putty works under progress.
Tiling work under progress.
Plumbing work under progress.
Internal electrification work under progress.
External plastering work completed.
CLUSTER 22(ROW HOUSE NO. 148-152):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed.
Door shutter work completed.
Window work completed.
Plumbing work completed.
Internal electrification work completed.
External plastering work & external painting work completed.
CLUSTER 23(ROW HOUSE NO. 138-147):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed.
Door shutter work under progress.
Window work completed.
Internal putty work under progress.
Tiling work completed.
Plumbing work completed.
External plastering work completed and external painting work under progress.
CLUSTER 24(ROW HOUSE NO. 117 ):
Civil sub structure work under completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 26(ROW HOUSE NO. 118-127):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed & under progress for other Phases.
Door frame fixing work completed & under progress for other Phases.
Door shutter work completed.
Window work completed & under progress for other Phases.
Internal putty work completed & under progress for other Phases.
Tiling work completed & under progress for other Phases.
Plumbing work completed & under progress for other Phases.
Internal electrification work completed & under progress for other Phases.
External plastering work & painting work completed & under progress for other Phases.
CLUSTER 27(ROW HOUSE NO. 107-115):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed & under progress for other Phases.
Door shutter work completed & under progress for other Phases.
Window work completed & under progress for other Phases.
Internal putty work completed & under progress for other Phases.
Tiling work under completed & under progress for other Phases.
Plumbing work completed & under progress for other Phases.
Internal electrification work completed & under progress for other Phases.
External plastering work & painting work completed & under progress for other Phases.
CLUSTER 28(ROW HOUSE NO. 128-137):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed
Door shutter work under progress.
Window work under progress.
Internal putty work under progress.
Tiling work under progress.
Plumbing work completed.
Internal electrification work progress.
External plastering work completed and external painting work under progress.
CLUSTER 29(ROW HOUSE NO. 98-106):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed
Window work completed.
Internal putty work under progress.
Tiling work under progress.
Plumbing work completed.
Internal electrification work completed.
External plastering work completed.
CLUSTER 33(ROW HOUSE NO. 71-81):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed.
Door shutter work completed.
Window work completed.
Internal putty work completed.
Tiling work completed.
Plumbing work completed.
Internal electrification work completed.
External plastering work completed & painting work completed.
CLUSTER 34(ROW HOUSE NO. 53-64):
Civil sub structure work completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed.
Door shutter work completed.
Window work completed.
Internal putty work completed.
Tiling work completed.
Internal electrification work completed.
Plumbing work completed.
External plastering work completed & painting work completed.
CLUSTER 35(ROW HOUSE NO. 82-90):
Civil sub structure work completed for Phase I & under progress for other phases.
Civil super structure work completed for phase I & under progress for other phases
Internal brick works & plastering work completed for Phase I & under progress for other phases.
Internal electrification work completed for Phase I & under progress for other phases.
Door frame work completed for Phase I & under progress for other phases.
Window work under progress I & under progress for other phases.
Tiling work completed I & under progress for other phases.
Plumbing work completed I & under progress for other phases.
External plastering work completed I & under progress for other phases.
External plastering work completed & external painting work under progress.
CLUSTER 36(ROW HOUSE NO. 43-52):
Civil sub structure work completed for Phase I & under progress for other phases.
Civil super structure work completed for phase II & under progress for other phases.
Internal brick works & plastering work completed for Phase II & under progress for other phases.
Window work under progress Phase I & other phases.
Plumbing work under completed Phase I & under progress for other phases.
External plastering work completed Phase I & under progress for other phases.
CLUSTER 37(ROW HOUSE NO. 25-32):
Civil sub structure work under completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 38(ROW HOUSE NO. 33-40):
Civil sub structure work under completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 39(ROW HOUSE NO. 1-11):
Civil sub structure works completed.
Civil super structure work completed.
Internal brick work & plastering work completed.
Door frame fixing work completed.
Door shutter work completed.
Window work completed.
Internal putty work completed.
Tiling work completed.
Internal electrification work completed.
Plumbing work completed.
External plastering work completed & painting work completed.
CLUSTER 43(ROW HOUSE NO. 22 ):
Civil sub structure work under completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 44(ROW HOUSE NO. 23 ):
Civil sub structure work under completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 45(ROW HOUSE NO. 24):
Civil sub structure work under completed.
Civil super structure work under progress.
Internal brick work under progress.
CLUSTER 46(ROW HOUSE NO. 65-70 ):
Civil sub structure work under completed.
Civil super structure works completed.
Internal brick work under progress.
Inside & outside area plaster under progress.
Club:
Civil sub structure work completed.
Civil super structure work completed.
Roof floor slab casting completed
Internal brick work completed for inside & outside area plaster completed.
Window work completed.
Plumbing work completed.
External plastering work completed.
Finishing work under progress.