AS ON 01.06.2023
BLOCK-B(WING-1)
External paint work is in progress.
BLOCK-B(WING-2)
Paintwork is in progress at the club.
External paint work is in progress.
BLOCK-C
Piling work in progress.
BLOCK-A
The 11th-floor Internal Plaster work is completed.
External Plastering work in progress.
The 9th-floor Tiles work is completed, 10th & 11th-floor work is in progress.
The 10th-floor Internal Ceiling work is completed & 11th-floor work is in progress.
Internal Wall Putty work is completed up to the 6th floor & 7th-floor work is in progress.
INFRASTRUCTURE WORK:
Underground reservoir completed.
Rainwater Harvesting 1 no tank completed & 1 no work in progress.
STP civil work is completed. Electro-Mechanical work in progress.
Road work in progress.
Landscape work on progress.