ERROR:
Javascript not activated
×
AS ON 01.05.2022
BLOCK-28
Foundation work completed.
Slab casting work completed, 11th floor brick work completed
7th floor internal plastering work completed.
BLOCK-29
Piling work completed.
BLOCK-34
Piling work completed.
Foundation work completed.
2nd floor slab casting work in progress.
BLOCK-35
Piling work completed.
Foundation work completed.
BLOCK-38
Piling work in progress.
BLOCK-39
Foundation work completed.
4th floor slab casting work in progress.
BLOCK-40
Foundation work, final slab casting work and brick work completed.
Internal plastering work completed.
3rd - 10th floor flooring work completed.