AS ON 01.11.2024
BLOCK-3
Piling work in progress.
Pile Cap excavation work In progress.
BLOCK-4
1st floor column reinforcement.
Shuttering work In progress.
BLOCK-5
7th floor level column shuttering & reinforcement work in progress.
2nd floor brick work in progress.
2nd floor internal brick work completed.
BLOCK-6
External primer work in progress.
Electrical work in progress.
Above roof floor work in progress.
BLOCK-7
Above roof floor work in progress.
Lobby,staircase floor tiles work In progress.
Internal flat putty work In progress.
Aluminium work in progress.
External primer work in progress.
BLOCK-8
Above roof floor work in progress.
External plaster work in progress.
Toilet balcony waterproofing work in progress.
BLOCK-9
6th floor column shuttering & reinforcement work in progress.
2nd floor brick work in progress.
1st floor Internal Brick work completed.