AS ON 01.10.2024
PHASE-I
CLUSTER - 03 (BUNGALOW HOUSE NO. 11 - 15)
Civil sub structure works complete.
Ground floor slab completed.
1st floor slab completed.
Roof slab completed.
Brickwork completed.
Plastering work completed
Internal Electrical Wiring work completed.
Internal Plumbing work in progress.
Water Proofing is completed.
POP work in progress.
Anti termite work completed.
Flooring work is in progress.
External paint is in progress.
Finishing work is on progress.
CLUSTER - 04 (BUNGALOW HOUSE NO. 16 - 21)
Civil substructure works foundation completed.
Ground floor slab completed.
1st floor slab completed.
Brickwork in progress.
Roof slab is completed.
Electrical work is in progress.
Internal Plumbing work in progress.
Plastering work in progress.
Anti termite work completed.
Waterproofing completed.
Flooring work is in progress.
External paint work is in progress.
Finishing work is in progress.
CLUSTER - 15 (BUNGALOW HOUSE NO. 57 - 59)
Civil substructure works foundation complete.
Ground Floor slab completed.
1st floor slab completed.
Roof slab completed.
Brickwork completed.
Plastering work completed.
Internal Electrical wiring work is completed.
Internal Plumbing work in progress.
Water Proofing work completed.
POP work in progress.
Anti termite work completed.
Flooring work in progress.
External paint work is in progress.
Finishing work is in progress.
CLUSTER - 16 (BUNGALOW HOUSE NO. 34 - 37)
Civil substructure works complete.
Civil superstructure works complete.
Ground floor slab completed..
1st floor slab is completed.
Roof slab completed.
Brickwork completed.
Plastering work completed.
Internal Plumbing work in progress.
Internal Electrical Work is in progress.
Water Proofing completed.
Pop work in progress.
Anti termite work completed.
Flooring work in progress.
External paint work is in progress.
Finishing work is in progress.
CLUSTER - 17 (BUNGALOW HOUSE NO. 26 - 33)
Civil substructure works foundation completed.
Ground floor slab completed.
Brickwork in progress.
1st floor slab completed.
Internal Electrical work in progress.
Roof slab is completed.
Plastering work in progress.
Internal Plumbing work in progress.
Anti termite work completed.
Water Proofing work in progress.
Flooring work in progress. (Except-27)
External paint work is in progress.
Finishing work is in progress.(Except-27)
CLUSTER - 19 (BUNGALOW HOUSE NO. 38 - 47)
Civil substructure works foundation completed.
Ground floor slab completed.
Brickwork work in progress.
1st floor slab completed.
Internal Electrical Wiring work in progress.
Roof slab completed.
Plastering work in progress.
Internal Plumbing work in progress.
Anti termite work completed.
Waterproofing work completed.
Flooring Work in progress.
External paint work is in progress.
Finishing work is in progress.
CLUSTER - 20 (BUNGALOW HOUSE NO. 48 - 56)
Civil substructure works foundation completed.
Ground floor slab completed.
Brickwork in progress.
1st floor slab completed.
Internal Electrical Wiring work in progress.
Roof slab completed.
Plastering work in progress.
Internal Plumbing work in progress.
Pop work in progress.
Anti termite work completed.
Waterproofing work is in progress.
Flooring Work in progress.
External paint work is in progress.
Finishing work is in progress.
CLUSTER - 21 (BUNGALOW HOUSE NO. 63 - 70)
Civil substructure works foundation completed.
Ground floor slab completed.
1st floor slab completed.
Roof slab is completed.
Brickwork work in progress.
Internal Electrical Wiring work in progress.
Plastering work in progress.
Internal Plumbing work in progress.
Anti termite work completed.
Waterproofing work is in progress.
Flooring Work in progress(63 to 70).
External paint is in progress.
Finishing work is in progress.
CLUSTER - 22 (BUNGALOW HOUSE NO. 71 - 78)
Civil substructure works foundation completed.
Ground floor slab completed.
1st floor slab completed.
Roof slab completed.
Brickwork is completed.
Internal Electrical work is completed..
Plastering work is completed.
Internal Plumbing work in progress.
Pop work in progress.
Anti termite work completed.
Waterproofing work is in progress.
Flooring work is in progress.(71 to 78)
Finishing work in progress.(72,73,74,75,78).
CLUSTER - 23 (BUNGALOW HOUSE NO. 87 - 92)
Civil substructure works foundation completed.
Ground Floor Slab completed.
1st floor slab completed.
Roof slab completed.
Brickwork work in progress. ( 87 to 92)
Internal Electrical work in progress.
Plumbing work in progress.
Plastering work in progress.
Anti termite work completed.
Waterproofing work is in progress.
Flooring work is in progress.(87 to 89)
External paint is in progress.
Finishing work is in progress.
CLUSTER - 29 (BUNGALOW HOUSE NO. 98 - 99)
Civil substructure works foundation completed.
Ground floor slab is completed.
Brick work is in progress.
1st floor slab completed.
Roof slab completed.
Internal Electrical work in progress.
Plumbing work in progress.
Plastering work in progress.
External paint is in progress.
Flooring work is in progress.
CLUSTER - 30 (BUNGALOW HOUSE NO. 93 - 97)
Civil substructure works completed.
Ground Floor Slab completed.
1st floor slab completed.
Roof slab is completed.
Brickwork work is in progress.
Internal Electrical work in progress.
Plaster work is in progress.
Plumbing work is in progress.
Anti termite work completed.
Waterproofing work is in progress.
Flooring work is in progress(93 to 97).
Finishing work is in progress.
CLUSTER - 31 (BUNGALOW HOUSE NO. 83 - 86)
Civil substructure works foundation completed.
Ground Floor Slab completed.
1st floor slab completed.
Brickwork work is in progress.
Roof slab is completed.
Plaster work is in progress.
Anti termite work completed.
Waterproofing work in progress.
External paint is in progress.
Flooring work is in progress(83 to 96).
Finishing work is in progress.
CLUSTER - 32 (BUNGALOW HOUSE NO. 79 - 82)
Civil substructure works foundation completed.
Ground Floor Slab completed.
1st floor slab completed
Brickwork in progress.
Internal Electrical work in progress.
Roof slab is completed.
Plastering work in progress.
Internal Plumbing work in progress.
Anti termite work completed.
Flooring work is in progress.
Waterproofing work is in progress.
External paint is in progress.
Finishing work is in progress.
CLUSTER - 33 (BUNGALOW HOUSE NO. 60 - 62)
Civil substructure works foundation completed.
Ground floor slab completed.
1st floor slab completed.
Brickwork in progress.
Roof slab is completed.
Internal Electrical work in progress.
Plastering work in progress.
Plumbing work in progress.
Anti termite work completed.
Flooring work is in progress.
Waterproofing work is in progress.
External paint is in progress.
Finishing work is in progress.
CLUB
Piling completed.
Excavation work in progress.
Basement Raft Completed.
Retaining Wall completed.
Ground floor slab completed.
ROAD
Flooring work of road is in progress at cl- 3 & 4 ,cl- 17 & 19, cl- 15 & 33, cl- 20 & 21, 22 & 23,31 & 32, 29 & 30.
Landscape work is started.
PHASE-II
CLUSTER - 6 (Unit no. 190 to 203)
Pile works is in progress. (190,191)
CLUSTER - 7 (Unit no. 184 to 189)
Pile works is completed (184,185)
CLUSTER - 8 (Unit no. 181 - 183)
Pile works is completed.
CLUSTER - 9 (Unit no. 175 - 180)
Pile works is completed.
CLUSTER - 13 (Unit no. 131 - 151 & 212)
Pile works is completed (147 to 151 & 212).
CLUSTER - 15 (Unit no. 122 - 126)
Civil sub structure work is completed (122 to 125).
CLUSTER - 23 (Unit no. 174)
Civil sub structure work is completed.
CLUSTER - 24 (Unit no. 158 - 162)
Pile works is in progress(158,159,160).
CLUSTER - 25 (Unit no. 163 - 167)
Pile works is completed.
CLUSTER - 29 (Unit no. 106 - 109)
Pile works is completed.
Sub structure work is in progress.
CLUSTER - 32 (Unit no. 115 - 118)
Sub structure (foundation) is completed.
Ground floor slab is completed.(115 to 118)